The Reporter covers Miller, Morgan and Camden County in Central Missouri's Lake of the Ozarks and is published once per week on Wednesdays.
Published February 14, 2018
$50,000 to fix water line?
CAMDENTON – Water was the main topic of discussion at last week’s Board of
Aldermen meeting.
A large part of the meeting time was taken up with a discussion about a water
line that is outside the city limits.
“City staff has informed the board that the city has not found documentation on
how a water line at Southside Drive and outside the city limits became part of
the city system,” a report to the Board of Aldermen stated.
Apparently many years ago (maybe several decades) a water line was hooked to the
city water system to serve residences just outside the city limits.
During the discussion last week Mayor John McNabb stated that the city has
reviewed past records and could not find any place where the board voted to
approve the water connection.
Despite that, the city has been supplying water and collecting fees from the
residences during that time and has performed all repairs on the water line over
the years.
The water line is a two-inch galvanized line that is consistently failing and,
according to Director of Public Works Bill Jeffries, was not put in to
specifications required by the Missouri Department of Natural Resources or the
city.
According to Jeffries, in some areas the line is only eight inches below the
ground which contributes to the line freezing in cold weather.
“To thaw the line requires digging up about 30 to 40 feet of line and 40 man
hours,” Jeffries told the board. “The condition of the line requires repair due
to leaks anywhere between four to twelve times per year.”
One of the problems is that there are very few residences on the line and the
city estimates it would cost them approximately $50,000 to replace the main
line.
One solution is for the residences to hook on to water (located nearby) from
Public Water Supply District #2 (PWSD #2).
During the discussion it was stated that the last time the matter was discussed
between the city and PWSD #2, they would take over the situation if Camdenton
would pay for the water main.
Since the water main is outside the city limits and they have not found minutes
of the board approving the water line, spending that much city money is not a
favorable solution.
Two owners of property on Southside Drive were at the meeting and expressed
their opinions on the matter and also stated that the residents themselves
cannot afford to pay for the line either to the city or to the PWSD #2.
Drilling a well for each piece of property would also be costly for the property
owners.
The two who spoke at the meeting gave the impression that despite the city not
finding any proof they ever approved the line, by collecting fees and doing
repairs over the years the city has claimed ownership of it and they are
responsible for the line.
It was also stated that the Public Works Department spent approximately $2,500
in labor and $2,500 in materials and supplies and also indicated that this year
was the least amount that was annually spent.
One solution given in the report to the board was to give adequate notification
to the residents and then stop supplying them water leaving them to fend for
themselves.
“Since the area is outside the City limits and since there are some private
wells in the area and a Pubic Water District within the area that might be able
to service these residents, one of the options recently discussed is that after
the City giving adequate notice to the owners and residents, the City might
consider abandoning this line and request that the owners review and act on
other options for water service.”
The board agreed to do some more research and check with PWSD #2 to see if a
solution can be found.
The other water item addressed by the board last week was the approval of a
contract with Drill Tech Inc. for the 2017 two-inch Water Line Replacement
Project.
The total project includes two-inch waterline replacement on Helms St., Lakeview
Circle, Poplar St., Roofener St., South High St., South Ozark St., and South
Business 5.
This project received 13 bids, with Drill Tech winning the project with a bid of
$207,370. This is $38,933 lower than his engineer’s estimate of $246,303.75.
The other bidders and their total bid amounts were:
• $374,738.25 from Reinhold Electric
• $312,247 from Do-Rite
• $281,940.05 from Orr Wyatt Streetscapes
• $264,170 from Travis Hodge Excavation and Hauling
• $257,753.34 from S&A Equipment
• $253,965 from RC Contracting
• $253,796 from Apperson Utility Contracting Inc.
• $253,185 from M&M Landscaping
• $244,413 from Donald Maggi Inc.
• $243,875 from Rhad Baker construction
• $237,998.40 from RAB Trenchless Solutions LLC
• $237,596.19 from Cody Martin Excavating
• $207,370 from Drill Tech
In other business at last week’s Board of Aldermen meeting:
• The board approved a name change for the Huelett Lagoon. Apparently it never
had an official name but received its name because of its location.
Due to the controversy concerning the water contamination, the city voted to
change the name of the lagoon to Lagoon #3 so people don’t associate it with the
Huelett automobile dealership, which has nothing to do with the lagoon.
• Accepted the 2017 independent audit
• Agreed to an early termination of a hangar at the airport. There is a waiting
list for hangar space so it should be filled very quickly.
• Approved the hiring of a Park Recreation Specialist
• Issued two proclamations, one for Ronald McDonald House and the other for
Career and Technical Education Month
All content is Copyright 2018 by Reporter Publishing, L.L.C. Unauthorized reproduction is prohibited without written permission.